York Street Power

Power generation for AI infrastructure and energy

Send a requirement

Travers AI Data Centre Campus

Local landowner (company not disclosed), Near the Travers Reservoir, Vulcan County, AB

Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.

Announced

Not stated

announced

Not stated

energized

Vulcan County council rezoned about 350 hectares for an AI data centre in June 2026. The proponent says it would grow to about 1,000 MW of IT load over several phases. In October 2026 a court agreed to review the rezoning at residents' request.

Where it standsNo entry on AESO’s connection list carries its name, and Alberta’s interim grid capacity has already been allocated.


Power path
Grid
Setup
Not stated
Utility
AESO
Connection request
Not stated
Target online
Not stated
Announced
2026-06-10

Getting power in Alberta

Bring your own generation. The Alberta record covers how projects get power there and what is changing.

Sources

Other tracked projects in Alberta


Updated 2026-11-10.

External document

The publisher’s own file. It may download rather than open.

Open the document