No cap. You connect through IESO and the transmitter, usually Hydro One.
The hold-ups are the province’s unfinished approval rules and municipal land use.
- Your own power
- Legal. Some large tech companies are looking at it to avoid transmission waits.
- Cost
- No data centre rate yet; one has been proposed.
- Latest
- Mississauga paused data centres of 10 MW or more for up to a year on 16 September 2026.
3 years or more to connect, IESO's figure for new facilities 13 projects Full Ontario record