Beacon AI Hub, Heartland

Beacon AI Centers, Section 15-56-22-W4, about 7 km east of Gibbons, Sturgeon County, AB

Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.

Filed for connection

800 MW

announcedpower for the data halls

0 MW

energized

None of it is built and energized yet.

A 920 MW gas plant about 7 km east of Gibbons in Sturgeon County, of which about 800 MW would power on-site data halls. The AUC approved the plant, with conditions, on 23 October 2026. AESO also lists two Beacon Heartland grid load requests of 400 MW each.

Where it standsIt is on AESO’s connection list, but AESO has given it no in-service date. Its power plan combines the grid with dedicated generation.


Power path
Hybrid
Setup
920 MW gas plant of about 200 reciprocating engines
Utility
AESO
Connection request
AESO P2934 Beacon Heartland A.I. Hub Load (400 MW), P3175 Beacon Heartland Data Load (400 MW)
Target online
Not stated
Announced
Not stated

Filed with the system operator

From AESO's connection list.

Reference Stage Filed In service Status
P2934 EN1 400 MW No date No date yet
P3175 EN1 400 MW No date No date yet

2 entries, 800 MW as filed.

Getting power in Alberta

Bring your own generation. The Alberta record covers how projects get power there and what is changing.

Sources

Other tracked projects in Alberta


Updated 2026-11-10.