Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.
Filed for connection
1.5 GW
announced
0 MW
energized
None of it is built and energized yet.
Capital Power proposes a data centre of up to 1,500 MW at its Genesee Generating Station. It did not get enough power under AESO's first round. AESO has two requests on file, 1,000 MW and 500 MW, with no in-service date. Capital Power says it is still exploring opportunities with AI companies and data centre developers, and is reviewing a dedicated power plant under AESO's rules for projects that bring their own generation.
Where it standsIt is on AESO’s connection list, but AESO has given it no in-service date.
- 2024-06-26 Filed with the operator 1,500 MW filed
- 2025-07-30 Announced
- No date In service the operator has set no date
- Power path
- Grid
- Setup
- Next to the Genesee gas plant
- Utility
- AESO
- Connection request
- AESO P2942 Genesee Data Center 1 MPC Load (1,000 MW), P2946 Genesee Data Center 2 MPC Load (500 MW)
- Target online
- Not stated
- Announced
- 2025-07-30
Filed with the system operator
From AESO's connection list.
| Reference | Stage | Filed | In service | Status |
|---|---|---|---|---|
| P2942 | EN1 | 1,000 MW | No date | No date yet |
| P2946 | EN1 | 500 MW | No date | No date yet |
2 entries, 1,500 MW as filed.
Getting power in Alberta
Bring your own generation. The Alberta record covers how projects get power there and what is changing.
Sources
- Proposed Genesee Data Centre Project Update
- AESO Connection Project List, October 2026
- Capital Power still waiting for Alberta data centre powering opportunity
Other tracked projects in Alberta
- Wonder Valley AI Data Centre Park, Phase 1 O'Leary Ventures · 1.4 GW · Announced
- Wild Rose Data Centre BHE Canada · 1.3 GW · Filed for connection
- Beacon AI Hub, Indus Beacon AI Centers · 1.2 GW · Announced
- Meta Data Centre, Sturgeon County Meta · 1.0 GW · Construction
- Synapse Olds Data Centre Synapse Data Center Inc. · 1.0 GW · Not approved
- Malachite One Data Centre Emerald Energy Technologies (Tourmaline Oil) · 1.0 GW · Announced
- Beacon AI Hub, Heartland Beacon AI Centers · 800 MW · Filed for connection
- Beacon AI Data Centre Hub, Chestermere Beacon AI Centers · 400 MW · Announced
Updated 2026-11-10.