1.0 GW

announced

0 MW

energized

Meta broke ground in July 2026 on a $13B+, 1 GW campus, its first data centre in Canada. AESO has 970 MW on file for it, 60 MW from May 2027 and the rest from September 2030, one of two projects given grid capacity in Phase 1. Capital Power supplies 250 MW from the second half of 2028, and the 932 MW Greenlight gas plant next door is due in the second half of 2030.

Where it standsUnder construction. AESO’s dates put its first 60 MW on the grid in May 2027 and its last stage in September 2030. Its power plan combines the grid with dedicated generation.

  1. 2024-05-14 Filed with the operator 1,800 MW filed
  2. 2026-07-08 Announced
  3. 2027-05-01 In service

Power path
Hybrid
Setup
Grid power, with Capital Power supply and the Greenlight gas plant next door
Utility
AESO
Connection request
AESO P2936 GLDC Load Phase 1.1 (970 MW), P3151 GLDC Load Phase 1.2 (830 MW)
Target online
Not stated
Announced
2026-07-08

Filed with the system operator

From AESO's connection list.

Reference Stage Filed In service Status
P2936
  • EN1 60 MW 2027-05-01
  • EN2 910 MW 2030-09-01
970 MW 2027-05-01 Dated
P3151 EN1 830 MW No date No date yet

2 entries, 1,800 MW as filed.

Getting power in Alberta

Bring your own generation. The Alberta record covers how projects get power there and what is changing.

Sources

Other tracked projects in Alberta


Updated 2026-10-15.

External document

The publisher’s own file. It may download rather than open.

Open the document