Telus AI Data Centre, 150 West Georgia

Telus, 150 West Georgia Street , Vancouver, BC

Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.

Announced

Not stated

announced

Not stated

energized

A Telus AI data centre at 150 West Georgia Street, built on top of Creative Energy's district steam plant and cooled by a closed liquid loop, due online in 2029. Part of Telus's three-site network sharing 85 MW from BC Hydro.

Where it standsTelus says it has secured an initial 85 MW from BC Hydro for its AI factories. The company targets 2029.

  1. 2026-05-12 Announced
  2. 2029 Developer target

Power path
Grid
Setup
Grid power, liquid-cooled, above a district steam plant
Utility
BC Hydro
Connection request
Not stated
Target online
2029
Announced
2026-05-12

Getting power in British Columbia

Competitive call. The British Columbia record covers how projects get power there and what is changing.