Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.
Announced
400 MW
announced
0 MW
energized
None of it is built and energized yet.
Two more Bell AI Fabric sites in British Columbia, which Bell says total more than 400 MW and are in advanced planning. Bell has not named the locations.
Where it standsIn BC Hydro’s area a new data centre over 10 MW gets power through a Call for Demand, unless it was already in BC Hydro’s study process; the first call’s results are still pending.
Not shown on the map. No location has been disclosed for this project beyond British Columbia, sites not named. Its megawatts are counted in every total on this site; only the dot is withheld, because placing one would assert a site nobody has stated.
- Power path
- Grid
- Setup
- Grid power
- Utility
- BC Hydro
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- 2025-05-28
Getting power in British Columbia
Competitive call. The British Columbia record covers how projects get power there and what is changing.
Sources
Other tracked projects in British Columbia
- IREN Mackenzie IREN · 100 MW · Operating
- DMG Christina Lake DMG Blockchain Solutions · 75 MW · Operating
- IREN Prince George IREN · 50 MW · Operating
- IREN Canal Flats IREN · 30 MW · Operating
- Bell AI Fabric Kamloops, TRU campus Bell Canada with Thompson Rivers University · 26 MW · Construction
- Bell AI Fabric Kamloops, second site Bell Canada · 26 MW · Announced
- Bell AI Fabric Kamloops Bell Canada with Groq · 7 MW · Operating
- Bell AI Fabric Merritt Bell Canada (Buzz HPC as tenant) · 7 MW · Operating
Updated 2026-10-14.