Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.
Operating
100 MW
announced
80 MW
energized
80 MW of the 100 MW announced is built and energized. How much power it actually uses is not published.
Running at 80 MW since December 2022; IREN now describes Mackenzie as a 100 MW site. IREN is replacing bitcoin miners with GPUs here, backed by a US$2.4 billion financing in August 2026, and in November 2026 said construction of new liquid-cooled data centres had begun.
Where it standsRunning, with 80 MW energized of the 100 MW the company has announced.
- Power path
- Grid
- Setup
- Bitcoin mining, converting to AI cloud computing
- Utility
- BC Hydro
- Connection request
- Not stated
- Target online
- 2022
- Announced
- Not stated
Getting power in British Columbia
Competitive call. The British Columbia record covers how projects get power there and what is changing.
Sources
Other tracked projects in British Columbia
- Bell AI Fabric, two more BC sites Bell Canada · 400 MW · Announced
- DMG Christina Lake DMG Blockchain Solutions · 75 MW · Operating
- IREN Prince George IREN · 50 MW · Operating
- IREN Canal Flats IREN · 30 MW · Operating
- Bell AI Fabric Kamloops, TRU campus Bell Canada with Thompson Rivers University · 26 MW · Construction
- Bell AI Fabric Kamloops, second site Bell Canada · 26 MW · Announced
- Bell AI Fabric Kamloops Bell Canada with Groq · 7 MW · Operating
- Bell AI Fabric Merritt Bell Canada (Buzz HPC as tenant) · 7 MW · Operating
Updated 2026-11-10.