Announced
Not stated
announced
Not stated
energized
A 575-acre data centre campus. In August 2026 Wheatland County council rezoned the land for industrial use on a 4 to 3 vote. AESO lists it as Goldfinch Technology Park MPC Load, 950 MW in two stages, under review. Diode says it is working with AESO on how much power can be supplied and will pay for the grid upgrades.
Where it standsIt is on AESO’s connection list, but AESO has given it no in-service date.
- 2025-03-19 Filed with the operator 950 MW filed
- 2026-09-03 Announced
- No date In service the operator has set no date
- Power path
- Grid
- Setup
- Not stated
- Utility
- AESO
- Connection request
- AESO P3102 Goldfinch Technology Park MPC Load (950 MW)
- Target online
- Not stated
- Announced
- 2026-09-03
Filed with the system operator
From AESO's connection list.
| Reference | Stage | Filed | In service | Status |
|---|---|---|---|---|
| P3102 |
| 950 MW | No date | No date yet |
One entry, 950 MW as filed.
Getting power in Alberta
Bring your own generation. The Alberta record covers how projects get power there and what is changing.
Sources
Other tracked projects in Alberta
- Genesee Data Centre Capital Power · 1.5 GW · Filed for connection
- Wonder Valley AI Data Centre Park, Phase 1 O'Leary Ventures · 1.4 GW · Announced
- Wild Rose Data Centre BHE Canada · 1.3 GW · Filed for connection
- Beacon AI Hub, Indus Beacon AI Centers · 1.2 GW · Announced
- Meta Data Centre, Sturgeon County Meta · 1.0 GW · Construction
- Synapse Olds Data Centre Synapse Data Center Inc. · 1.0 GW · Not approved
- Malachite One Data Centre Emerald Energy Technologies (Tourmaline Oil) · 1.0 GW · Announced
- Beacon AI Hub, Heartland Beacon AI Centers · 800 MW · Filed for connection
Updated 2026-11-10.