Cologix MTL8

Cologix, 7350 rue Frederick-Banting, Saint-Laurent , QC

Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.

Operating

21 MW

announced

Not stated

energized

A 21 MW, 206,000 sq ft colocation data centre near Montreal's airport, built for AI workloads. La Caisse provided C$240 million in senior debt in March 2026.

Where it standsRunning. The company has announced 21 MW; how much of it is energized is not stated.


Power path
Grid
Setup
Hydro-Québec grid
Utility
Hydro-Québec
Connection request
Not stated
Target online
Not stated
Announced
2026-03-05

Getting power in Quebec

Ministerial authorization. The Quebec record covers how projects get power there and what is changing.