Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.
Operating
86 MW
announced
Not stated
energized
A four-building, 86 MW campus on 30 acres in Quebec City's high-tech park. The first three buildings are running, and the fourth, QC24 at 32 MW, is under construction and due to be operational in early 2027, according to Vantage.
Where it standsRunning. The company has announced 86 MW; how much of it is energized is not stated.
- 2025-02-27 Announced
- 2027 Developer target
- Power path
- Grid
- Setup
- Hydro grid
- Utility
- Hydro-Québec
- Connection request
- Not stated
- Target online
- 2027
- Announced
- 2025-02-27
Getting power in Quebec
Ministerial authorization. The Quebec record covers how projects get power there and what is changing.
Sources
- Vantage Data Centers Invests $500 Million CAD to Drive Economic Growth, Sustainability and Innovation in Quebec
- Quebec City Data Center Campus
Other tracked projects in Quebec
- QScale Q01 Campus QScale · 142 MW · Operating
- Gatineau Data Hub AVAIO Digital Partners / Société immobilière ADAM · 50 MW · Not approved
- Keel Sherbrooke, Bunker Keel Infrastructure (formerly Bitfarms) · 48 MW · Operating
- HIVE Lachute HIVE Digital · 34.5 MW · Operating
- eStruxture MTL-2 eStruxture · 30 MW · Operating
- Vantage Montreal III Vantage Data Centers · 30 MW · Operating
- Keel Baie-Comeau Keel Infrastructure (formerly Bitfarms) · 30 MW · Operating
- Keel Sherbrooke, Léger Keel Infrastructure (formerly Bitfarms) · 30 MW · Operating
Updated 2026-11-10.