Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.
Operating
30 MW
announcedcontracted power
22 MW
energized
22 MW of the 30 MW (contracted power) is built and energized. How much power it actually uses is not published.
A 22 MW bitcoin mine in a leased building on Baie-Comeau's municipal power network. In September 2026 the city raised the site's contracted power from 22 to 30 MW and allowed all of it to be used for data centres, including AI. Keel, formerly Bitfarms, says it expects bitcoin mining to wind down gradually as it builds data centres.
Where it standsRunning, with 22 MW energized of the 30 MW the company has announced.
- Power path
- Grid
- Setup
- Hydro grid, bitcoin mining
- Utility
- City of Baie-Comeau municipal network
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- Not stated
Getting power in Quebec
Ministerial authorization. The Quebec record covers how projects get power there and what is changing.
Sources
- Keel Infrastructure, third-quarter 2026 report
- Bitfarms Ltd. Form 10-K, fiscal year 2025
- Bitfarms Officially Rebrands as Keel Infrastructure; Completes U.S. Redomiciliation
Other tracked projects in Quebec
- QScale Q01 Campus QScale · 142 MW · Operating
- Vantage Quebec City Campus Vantage Data Centers · 86 MW · Operating
- Gatineau Data Hub AVAIO Digital Partners / Société immobilière ADAM · 50 MW · Not approved
- Keel Sherbrooke, Bunker Keel Infrastructure (formerly Bitfarms) · 48 MW · Operating
- HIVE Lachute HIVE Digital · 34.5 MW · Operating
- eStruxture MTL-2 eStruxture · 30 MW · Operating
- Vantage Montreal III Vantage Data Centers · 30 MW · Operating
- Keel Sherbrooke, Léger Keel Infrastructure (formerly Bitfarms) · 30 MW · Operating
Updated 2026-11-10.