York Street Power

Power generation for AI infrastructure and energy

Send a requirement

Vantage Montreal III

Vantage Data Centers, Baie-D’Urfé, QC

Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.

Operating

30 MW

announced

Not stated

energized

A single 30 MW building on an eight-acre site near Montréal-Trudeau airport, with its own 45 MW substation connected to Hydro-Québec. Vantage finished all phases in December 2025.

Where it standsRunning. The company has announced 30 MW; how much of it is energized is not stated.


Power path
Grid
Setup
Hydro grid, own 45 MW substation
Utility
Hydro-Québec
Connection request
Not stated
Target online
Not stated
Announced
Not stated

Getting power in Quebec

Ministerial authorization. The Quebec record covers how projects get power there and what is changing.

Sources

Other tracked projects in Quebec


Updated 2026-10-14.

External document

The publisher’s own file. It may download rather than open.

Open the document