Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.
Announced
7.2 MW
announced
0 MW
energized
None of it is built and energized yet.
BUZZ HPC bought a 7.2 MW site in the Greater Toronto Area in September 2025 to build a Tier III+ AI data centre. HIVE says it plans to energize this site and its other Canadian sites within 18 months of June 2026.
Where it standsOntario law lets the province set conditions on data centre connections, but no regulation applying them is in force yet; local grid capacity and municipal land use are what hold projects up.
Not shown on the map. No location has been disclosed for this project beyond Greater Toronto Area, ON. Its megawatts are counted in every total on this site; only the dot is withheld, because placing one would assert a site nobody has stated.
- Power path
- Grid
- Setup
- Grid power, liquid-cooled GPUs
- Utility
- Not stated
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- 2025-09-18
Getting power in Ontario
Grid, provincial approval in draft. The Ontario record covers how projects get power there and what is changing.
Sources
- BUZZ HPC Closes Acquisition of 7.2 MW Toronto Site
- HIVE Achieves FY2026 Total Revenue of $297.8 Million, HIVE's BUZZ HPC Positioned for Growth
Other tracked projects in Ontario
- Algoma AI Data Centre Red Jar Energy Partners and Algoma Steel · 400 MW · Filed for connection
- BUZZ HPC Greater Toronto AI Data Centre BUZZ HPC (HIVE Digital) · 320 MW · Announced
- STACK Toronto Campus STACK Infrastructure · 56 MW · Operating
- Cambridge AI Data Centre Related Digital, TowerBrook and Ascent · 54 MW · Operating
- Prologis Meadowvale Data Centre Prologis · 40 MW · Announced
- Compass Toronto Campus Compass Datacenters · 30 MW · Operating
- Yondr Toronto Data Centre Yondr · 27 MW · Operating
- 55H Brampton Data Centre 55H with CORE Data Centres · 20 MW · Operating
Updated 2026-11-10.