York Street Power

Power generation for AI infrastructure and energy

Send a requirement

Prologis Meadowvale Data Centre

Prologis, Tenth Line West and Argentia Road, Mississauga, ON

Tracked from public sources. A listing here does not mean York Street Power works with this project or its developer.

Announced

40 MW

announced

0 MW

energized

None of it is built and energized yet.

Under the Mississauga Interim Control By-law, passed 2026-09-16, for up to one year.

Prologis wants to rezone land at Tenth Line West and Argentia Road for a two-storey data centre with a peak demand of 40 MW, which it says is not a hyperscale AI site. Mississauga council has moved to pause new data centres of 10 MW or more for up to a year. Prologis has said it would not appeal to the Ontario Land Tribunal while its application stays in the city's review, though its representative had earlier said an appeal was likely.

Where it standsOntario law lets the province set conditions on data centre connections, but no regulation applying them is in force yet; local grid capacity and municipal land use are what hold projects up.


Power path
Grid
Setup
Grid power
Utility
Alectra Utilities
Connection request
Not stated
Target online
Not stated
Announced
2025-08-19

Getting power in Ontario

Grid, provincial approval in draft. The Ontario record covers how projects get power there and what is changing.

Sources

Other tracked projects in Ontario


Updated 2026-11-10.

External document

The publisher’s own file. It may download rather than open.

Open the document