Construction
5.5 MW
announced
0 MW
energized
Bell is converting the former Merit Functional Foods pea protein plant at CentrePort into a 5.5 MW AI data centre. Permits filed with the South Interlake Planning District cover at least $31.5 million of work.
Where it standsUnder construction.
- Power path
- Grid
- Setup
- Not stated
- Utility
- Manitoba Hydro
- Connection request
- Not stated
- Target online
- Not stated
- Announced
- 2026-04-29
Getting power in Manitoba